-
Summary of Rules and Deadlines
- SCR
- Lien
- Payment Bonds
-
Notice of Retention Rules
- What is a Notice of Retention?
- What are Preconstruction Services
- Who must file a Notice of Retention?
- What information must a Notice of Retention include?
- When must a Notice of Retention be filed?
- What happens if a Notice of Retention is not filed?
- Is a Notice of Retention required for private and public construction projects?
- Does more than one Notice of Retention have to be filed for each project?
-
Preliminary Notice Rules
- What is a Preliminary Notice?
- Who must file a Preliminary Notice?
- What information must a Preliminary Notice include?
- When must a Preliminary Notice be filed?
- What happens if a Preliminary Notice is not filed?
- Is a Preliminary Notice required for private and public construction projects?
- Does more than one Preliminary Notice have to be filed for each project?
- Good Faith Estimate of Completion
- Notice of Commencement Rules
- Notice of Completion Rules
-
Notice of Intention to File a Notice of Completion
- What is a Notice of Intention to File a Notice of Completion?
- When is a Notice of Intention to File a Notice of Completion filed?
- Who can file a Notice of Intention to File a Notice of Completion?
- What is the effect of filing a Notice of Intention to File a Notice of Completion?
- Must a Notice of Intention to File a Notice of Completion be filed for all construction projects?
-
Liens
-
Construction Service Lien
- What is a Construction Service Lien?
- Who may record a Construction Service Lien?
- What information must the Construction Service Lien contain?
- When must the Construction Service Lien be recorded?
- Where is the Construction Service Lien Recorded?
- Does a copy of the lien have to be to sent to anyone?
- May a single Construction Service Lien be used to lien more than one piece of property?
- Am I entitled to recover attorney fees or costs for preparing and recording a lien?
- After a Construction Service Lien is recorded, must any further action be taken to collect?
- After I have been paid do I have to release my lien?
-
Preconstruction Service Lien
- What is a Preconstruction Service Lien?
- Who may record a Preconstruction Service Lien?
- What information must the Preconstruction Service Lien Contain?
- When must the Preconstruction Service Lien be recorded?
- Where is the Preconstruction Service Lien recorded?
- Does a copy of the lien have to be sent to anyone?
- May a single Preconstruction Service Lien be used to lien more than one piece of property?
- Am I entitled to recover attorney fees or costs for preparing and recording a lien?
- After a Preconstruction Service Lien is recorded, must any further action be taken to collect?
- After I am paid do I have to release my lien?
- Lien Waivers
-
Construction Service Lien
-
Payment Bond Claims
- Public Property
- Private Property
-
Request for Adequate Assurance
- What is a Request for Adequate Assurance
- Who may make a Request for Adequate Assurance?
- When must a Request for Adequate Assurance be served
- Who receives the Request for Adequate Assurance?
- How is the Request for Adequate Assurance Served?
- What is the effect of serving a Request for Adequate Assurance?
- Is there a deadline to respond to a Request for Adequate Assurance?
- If I do not receive a response to my Request for Adequate Assurance, can I do anything about it?
A notice filed in the State Construction Registry indicating that a construction project is complete.
The general contractor, owner, lender, or title company.
Only after "final completion of the original contract", which typically means the day a permanent certificate of occupancy is issued:
Figure 6 Notice of Completion
This example shows the Certificate of Occupancy being issued on November 2. Once a Certificate of Occupancy is issued, the Notice of Completion can be filed at any time
Warning: Under the following circumstances, you cannot file a Notice of Completion unless you first file a Notice of Intent to File a Notice of Completion. The Notice of Intent to File a Notice of Completion is required when the project is: 1) privately owned; 2) total construction time exceeds 120 days; 3) total value of construction is greater than $500,000.00; and 4) no payment bond has been obtained by the owner/general contractor.
For instructions on filing a Notice of Intent to File a Notice of Completion, see the SCR Notice of Completion instructions above.
All Preliminary Notices are due within 10 days after the Notice of Completion, and all liens must be filed within 90 days after the Notice of Completion.