Notice of Commencement
  • Filed by the City, County, General Contractor or Owner
  • Due within 15 days from the date of the permit or commencement of physical construction (whichever is later)
  • If valid, restricts lien rights and payment bond rights to only those subcontractors and suppliers who file a Preliminary Notice

Preliminary Notice
  • Filed by subcontractors and suppliers
  • Due within 20 days after your first date of work
  • Preserves the right to file and enforce lien and bond claims

Notice of Intention to File Notice of Completion
  • Filed by the Owner, General Contractor, Surety, Lender, or Title Company
  • Due 45 days before a Notice of Completion
  • Requires subcontractors and suppliers to file a Good Faith Estimate of amount due

Notice of Completion
  • Filed by the Owner, General Contractor, Surety, Lender, or Title Company
  • May not be filed until Final Certificate of Occupancy or Final Inspection
  • Requires liens to be filed within 90 days from filing of the Notice of Completion

Good Faith Estimate of Value
  • Filed by subcontractors and suppliers
  • Due within 10 days after the filing of a Notice of Intention to File a Notice of Completion
  • Allows subcontractors and suppliers to demand assurance of finds for payment

 
 